| S No |
Payment Due On |
% age |
Other applicable charges |
| 1 |
Booking amount |
As applicable * |
|
| 2 |
On or before 2 months of the Application |
20% of BSP (Less booking amount*) |
|
| 3 |
On or before 4 months of the Application |
10% of BSP |
|
| 4 |
On commencement of excavation |
10% of BSP |
|
| 5 |
On laying of upper basement slab |
10% of BSP |
|
| 6 |
On laying of 1st floor Roof Slab |
7.5% of BSP |
Car park charges |
| 7 |
On laying of 3rd floor Roof Slab |
7.5% of BSP |
|
| 8 |
On laying of 6th floor Roof Slab |
6.5% of BSP |
IDC Charges |
| 9 |
On laying of 9th floor Roof Slab |
6.5% of BSP |
PLC Charges as applicable |
| 10 |
On laying of 11th floor Roof Slab |
6% of BSP |
Electric sub station charges |
| 11 |
On laying of top floor Roof Slab |
6% of BSP |
|
| 12 |
On completion of internal plaster & flooring within the apartment |
5% of BSP |
|
| 13 |
On offer of possession |
5% of BSP |
Social Club Charges + IFMD + Lease rent |
|
TOTAL |
100% |
|