Project Initiation
Document of Understanding Prepaparation and
getting all approval including Customer PM
If required Contract
Preparation.
Getting Space for the Project.
Getting Resources
for the Project.
Getting ThinkPad/Desktop for the
Project.
Doing all other procurement including separate
partition with access control for Banking Projects.
Project
Schedule Preparation
Project Monitoring and Control
Customer
Interaction(with customer PM)
Interaction with the
Team(offshore) and Team Leads(onsite)
Preparing Daily, Weekly
and Monthly status report
Prepare Quality Documents
Attend
Project Health Review, Quality Audit and Project Management
Review
Other PM Activities
Project Closure including Contract
review and then Closure