Projects are temporary in nature ; have definite start and end dates; produce a unique product ,service or a result; and are completed when their goals and objectives have been met and signed off by the stakeholders. Project Management is the seamless handling of multiple Projects. The Person who handles a project in Software Company or say any other company like a civil construction company is called a Project Manager and the considered individual ideally holds a PMP certification given by Project Management Institute (PMI) most of the companies where Project are handled have a PMO’s office where all the planning is done. Project Management is carried out in Stages 1] Initiation 2] Planning 3] Execution 4] Monitor & Control 5] Project Closure the same applies in Six Sigma Methods because Six Sigma is carried out in phases also which are 1] Define ( Similar to Initiation) 2] Measure 3] Analyze (Similar to Planning 4] Improve 5] Control ( Similar to Project Closure). Lean Six Sigma is all about removing variations and defects in a product or process. Like Project Management the lean Six Sigma Practioner needs to be certified by a governing body like IASSC, ASQ (American Society of Quality) or ISI(Indian Statistical Institute). The Certificates provided by them Lean Six Sigma Green Belt, Lean Six Sigma Black Belt & lean Six Sigma Master Black Belt.Bill Smith of Motorola Coined the term Six Sigma and is also called the father of Six Sigma; The Quality leader responsible for the term Total Quality Management is Feigen Baum; robustness in quality management was pioneered by Dr Taguchi; quality leader who did extensive work in Japanese industry is Dr Deming who paved the way for Quality Management Concept; Walter She wart is also one of the contributors in Six Sigma, he is sometimes referred to as father of Statistical Control.
The Table given below maps the phases of Six Sigma with that of Project Management Phases.
The Five Processes of PMP (Initiation, Planning, Execution, Monitor & Control, Closing Phase)
The relationship of the project stages to the life cycle phases
Stage |
Outputs |
Life Cycle Phases |
Starting the Project(Define Phase of Six Sigma) |
|
Initiating Process |
Organizing and Preparing |
|
Planning Process |
Carrying out the Work |
|
Execution Process Controlling and Monitoring Process
|
Closing out the Work(Control Phase of Six Sigma) |
|
Closing process |
Cost Benefit Analysis is done in Six Sigma as well as in the Initiation Phase of Project Management. Future value, Present Value and Net present Value formulas are also used in the Define Phase of Six Sigma as well as the Project initiation Phase of Project Management. Where the black belt or the Project Manager Should assess whether the project is worth doing.
Example Given Below:-
If $100,000 were invested for 5 years and managed to earn a interest of 6 % per year compounded annually it will be worth $133,822.60.
In other words if a Project says it will be earning the organization $160,000 per year in five years ,that’s great but what is $160,000 five years from now really worth today?
Project Planning
The planning process group has more processes than any other process group as a result a lot of time and effort goes into the planning process group of any company on some projects you might almost spend as much time planning with that of executing in a way it is a good sign as the project is properly planned.
The define activities process is the further breakdown of the work package elements of the WBS
Tools and techniques for defining activities
Precedence Diagramming Method (PDM)
The PDM Method is what most project management software programs use to sequence activities.
Precedence diagrams use boxes or rectangles to represent the activities called nodes the nodes are connected with arrows showing the dependencies this method is called AON activity on node. Diagram is given below.
The four dependencies are as follows
Finish to Start (FS) The finish to start relationship is the most frequently used relationship the relationship says that the predecessor or from activity must finish before the successor or to activity can start in PDM diagrams this is the most often used logical relationship.
Start to Finish (SF) The Start to finish relationship says that the predecessor activity must start before the successor activity can finish this logical relationship is seldom used.
Finish to Finish (FF) the finish to finish relationship says that the predecessor activity must finish before the successor activity finishes.
Start to Start (SS) the start to start relationship says that the predecessor activity depends on before the successive activity can start.
Critical Path Method (CPM) is a schedule network analysis technique it determines the amount of float or schedule flexibility for each network paths by calculating the earliest start date, earliest finish date , latest start date and latest finish date for each activity. The Critical path is generally the longest full path on the project any project activity with a float time of zero is considered a critical path task.
Calculating Expected Value : Say for example for a particular project you are given 38 days of optimistic time, 57 days for the pessimistic and 45 days for the most likely so the formula for calculating expected value is (Optimistic + pessimistic +(4* most likely))/6
The expected value for the sample project activity is as given below:-
(38 + 57+ (4*45))/6 = 45.83
The formula for standard deviation which helps to determine the confidence level is (pessimistic – optimistic)/6
The standard deviation for your activity is as follows (57-38)/6 = 3.17
So we subtract 3.17 – 45.83 = 42.66 and we conclude that there is 68.26 % chance that the project will be completed in 42.66 to 49 days.
Project Oversight and Management (Forecasting, Measurements & Monitoring):-
Every Project requires some measure of progress and in many cases, multiple forms of measurement must be used to gauge the overall health of the project, project measures might be used to answer basic questions like:
Let us consider some of the common forms of measures used on most projects at the task(work package) level
If SV is positive, the project is ahead of schedule, if the SV is zero the project is on schedule and if SV is negative, the project is behind schedule a corrective action must be taken.
CPI = EV/AC = BCWP/ACWP.
If the CPI is greater than 1 the project is under budget. If the CPI is equal to 1 , the project is on Budget and if the CPI is less than 1 , the project is over budget and corrective action must be taken.
SPI=EV/PV = BCWP/BCWS
If SPI is greater than 1, the project is ahead of schedule, if the SPI is equal to 1 the project is on schedule and if the SPI is less than 1 the project is behind schedule and corrective action should be taken.
We can conclude that the phases used in Six Sigma (DMAIC) & Project Management has nearly Similar activities in the respective phases which we have proved by mapping the two(Six Sigma & Project Management).